Wednesday, October 21, 2009

October 21, 2009

Cabinets were being installed today and look fantastic. (check out the pics) Crew is finishing the mudding and sanding of the drywall and the painters hope to begin this weekend. Cubbies you see in a few walls are for fire extinguishers. Carpenter was going to start hanging doors and the trim work today.

Cork flooring will be shipped on the 6th, need to wait until that is installed to install dishwasher and new refrigerator. MCT tile is backordered and looking at a Oct 15 ship date. Keep fingers crossed it is not any later than that to delay move.

Would like to take all staff for a visit in a week or so. Give you an opportunity to see your office space and visualize organizing it.